Significant revival in ISTS-TBCB landscape

There has been a noticeable revival in the number of interstate transmission system (ISTS) schemes awarded under the tariff-based competitive bidding (TBCB) route, in recent months.

 

Going by recent trends, the ongoing fiscal year FY24 will most likely to see the highest number of ISTS-TBCB schemes ever awarded in any year so far. During the period April 1, 2023 to around December 7, 2023 (roughly first three quarters of FY24), a total of 15 ISTS-TBCB schemes were awarded, according to an analysis by T&D India. At least six more schemes are likely to be awarded in the remaining period of FY24. This compares very favourably with 18 schemes awarded in FY23, nine in FY22 and three in FY21.

 

What is also conspicuous is that the power transmission developer base is witnessing increasing engagement from the private sector. In recent years, entities like GR Infraprojects, Megha Engineering and ReNew Power, to name a few, have joined the power transmission development space. It is also very heartening to note that a seasoned utility like Tata Power, which was largely away from the competitive bidding arena, recently made its debut by winning an ISTS-TBCB scheme in Rajasthan.

 

Most of the ISTS-TBCB schemes currently being awarded are related to renewable energy evacuation from RE-rich destinations like Gujarat, Rajasthan and Karnataka, among others. These projects, with a typical gestation period of 24 months, are being developed to support India’s massive RE ambition of 500 GW of installed power generation capacity from non-fossil fuels.

 

Today, there is much euphoria surrounding the 500-GW RE target – both on the generation and transmission side. However, it must be borne in mind that RE is a tricky business. From the generation perspective, the plant load factor is intrinsically low. This means that a given RE installed capacity will not result in the same electricity output as that of comparable conventional thermal power capacity. Besides, RE generation, due to its inherent intermittency, requires much technological intervention on the transmission side.

 

The true and full potential of renewable energy can therefore be realized only if RE generation is backed by grid-scale batter energy storage systems (BESS). India is making a sincere beginning in this domain but it will take some time before BESS establishes itself as an integral component of the T&D value chain.

 

It is therefore imminent that despite all the traction that RE is gaining, there will have to be a fast-track build-up of conventional (thermal) power generation capacity so as to forestall a shortfall in medium-term electricity demand.

 

 

The author of this article, Venugopal Pillai, is Editor, T&D India, and may be reached on venugopal.pillai@tndindia.com. Views expressed here are personal.

The curious case of KPS1 Transmission

First a bit of a background: KPS1 Transmission Ltd is a project special purpose vehicle (SPV) that was incorporated by bid process coordinator REC Power Development & Consultancy Ltd (RECPDCL) to develop an interstate transmission system (ISTS) scheme officially termed as “Transmission scheme for injection beyond 3 GW RE power at Khavda PS1 (KPS1)”.

 

After adopting the regular tariff-based competitive bidding (TBCB) procedure, Megha Engineering & Infrastructures Ltd (MEIL) was declared as the successful bidder, and the project SPV “KPS1 Transmission Ltd” was transferred to MEIL The transfer of the SPV took place around April 21, 2023, and this transfer symbolizes the formal “zero date” for the project that was expected to commissioned in 21 months thereafter.

 

In August 2023, Adani Energy Solutions Ltd (AESL), formerly Adani Transmission Ltd, announced that its board approved the proposal to acquire “KPS1 Transmission Ltd” from its original owner MEIL. As of September 30, 2023, this acquisition was complete as AESL showed KPS1 as one of its under-construction transmission projects, in an investor presentation filed on stock exchanges.

 

The takeover of TBCB assets is not new but the acquisition of KPS1 Transmission is unique in many respects. It is for the first time that a TBCB project has been acquired so early in its life. As of September 2023, when the acquisition was completed, MEIL had barely begun pre-project activities.

 

So far, acquisitions of TBCB projects are seen to have taken place after project was operational. Developers like Larsen & Toubro, Kalpataru Projects International Ltd, Techno Electric & Engineering have sold their operational TBCB assets as they wanted to exit the power transmission development space, and focus on EPC contracting.

 

There have also been cases where developers have sold their operational TBCB assets to infrastructure investment trusts like India Grid Trust (IndiGrid) and Powergrid Infrastructure Investment (PGInvIT).

 

There have also been instances where the developer was fraught with financial difficulties and the projects were stranded. This was the case with Essel Infraprojects, for example. These stranded assets were then acquired by other developers as part of the debt restructuring package worked out by lenders.

 

The acquisition of KPS1 Transmission by AESL, barely when the project has taken off, therefore stands out remarkably.

 

This acquisition has another dimension to it. In the initial bidding stage of KPS1 Transmission, four bidders had qualified – MEIL, Adani Transmission, Power Grid Corporation of India Ltd and Sterlite Power. However, in the final bidding stage, only three were qualified for submission of final bids, and in this, Adani Transmission did not feature. It is therefore interesting to see that a company that did not qualify to submit its bid for a project ultimately ended up acquiring it from the winning bidder.

 

In many respects, therefore, the case KPS1 Transmission AESL is strangely unique.

 

The author of this article, Venugopal Pillai, is Editor, T&D India, and may be reached on venugopal.pillai@tndindia.com. Views expressed here are personal.

Innovation should transcend technology domain

Industry body IEEMA recently held its Annual Convention that witnessed several keynote addresses on the broad subject of strategies for the new energy paradigm.

 

One such presentation dwelt on the subject of innovation. When we speak of innovation, what immediately comes to our mind is innovation in products or technologies. However, innovation need not, and should not, limit itself to technology. Innovation in areas like financing, for instance, needs attention. Innovative financing models can go a long way in making India’s infrastructure development a cost-effective exercise.

 

Some years ago, Energy Efficiency Services Ltd (EESL) devised the OPEX model – a true financial innovation – for funding the rollout of 5 lakh prepaid smart meters in Bihar. This was a huge success. In fact, it can be proudly recalled that during the pandemic years, when state power utilities were struggling to reach physical bills to its consumers, especially in rural and semi-urban areas, Bihar discoms were garnering revenues of up to Rs.5 lakh per day, thanks to prepaid smart metering and the inherent facility of digital payment.

 

Today, the RDSS envisages the TOTEX model that seeks to finance the rollout of a massive 25 crore smart prepaid meters, largely from funding from the private sector. Coming to think of it, the TOTEX model is a amplified extension of the OPEX model that EESL had introduced. This significant financial innovation is poised to have a huge positive impact, and that too nationwide.

 

Even when one speaks of technical innovation, the process is fraught with practical complexities. Companies that are engaged in manufacturing of electrical equipment, for instance, have immense scope for technological innovations. For instance, it is often spoken in industry circles that the basic design of a transformer has not changed from the time of Faraday! A transformer-less grid is hard to imagine but is it in the realms of possibility? Only serious innovation can provide the answer.

 

Companies are mostly engaged in day-to-day activities and the inclination towards innovation is limited, by design. This is also borne out in India’s low R&D expenses to GDP ratio. There are several startups and unicorns that devise technical innovations. However, these innovations cannot be deployed readily as they are generally futuristic in nature.

 

Hence, while technical innovations chug along, either through startups and R&D works of companies, there should be parallel emphasis on other forms of innovations like those on the financing or strategy side. Startups should be encouraged to devise financial innovations, and not just technical ones.

 

As financial innovations can generally be deployed with less lead time, they can contribute to overall cost-effectiveness and efficiency, which is after all ultimate aim of innovation.

 

The author is this post, Venugopal Pillai, is Editor, T&D India, and may be contacted on venugopal.pillai@tndindia.com. Views are personal

Time-of-day tariff is a big step forward

Policy reforms and technology intervention will hold the key to bringing commercial viability to India’s power distribution reforms. In the entire power value chain, it is the last-mile distribution where almost the entire commercial losses are concentrated. Resurrecting the power distribution space is therefore the only way to make the power value chain a profitable enterprise.

 

Very recently, the Union power ministry introduced “time of day (ToD)” tariffs. This was done by suitable amendments to the “Electricity (Rights of Consumers) Rules, 2020”.

 

ToD tariff marks a paradigm shift from the ubiquitous “same tariff” regime that has always been the historical norm. Basically, under the ToD mechanism, the electricity tariff will vary according to the time of the day (ToD). This can bring about a drastic change in the way electricity is consumed.

 

A consumer can now prefer to run heavy loads when tariffs are low. In other words, consumers will feel dissuaded to indulge in high electricity consumption when tariffs are high. This can, over a period of time, potentially flatten the peak demand curve.

 

It is not that the ToD tariff culture is entirely new to the nation; some private power distribution utilities have been experimenting with ToD tariffs on a pilot basis. In general, it is intuitively clear that electricity tariff in the day should be higher than that at night. This is for the simple reason that peak demand would exist during the day time when maximum consumption from industrial and commercial consumers takes place. However, now with renewable energy (mainly solar) expected to dominate the energy mix, tariff during solar hours (duration of eight hours as specified by the respective State Electricity Regulatory Commission) would be 10-20 per lower than normal tariff. In non-solar hours, tariff would be 10-20 per cent higher.

 

What ToD tariff is expected to do is to create “conscious” consumption of electricity. Right now, electricity is available practically round-the-clock – both in urban and rural areas. This makes electricity an “on-tap” commodity with consumption dictated by no factor other than need. When ToD comes into the picture, the dimension of tariff will set into the minds of the consumer. One can therefore expect that there electricity consumption will become judicious in nature.

 

The ToD facility will complement the benefits of smart prepaid metering. In a broad sense, while prepaid metering will ensure that power distribution companies become commercially viable (as monies will be collected before actual consumption of electricity), ToD tariff can help the consumer extract maximum electricity consumption for the payment made.

 

Two important benefits will accrue from the ToD tariff regime — rationalization and judicious management of electricity consumption. Both of these can prove effective agents of demand side management.

 

The author Venugopal Pillai is Editor, T&D India, and may be reached on venugopal.pillai@tndindia.com. Views are personal.

Making state governments more responsible

According to information recently tabled in Parliament, a preliminary study shows that India’s AT&C losses have climbed down to around 17 per cent in FY22 from around 22 per cent in FY21. This is based on information filed by 56 state government-owned discoms that account for more than 96 per cent of the country’s total input energy.

 

The decline in AT&C losses has resulted in a reduction in the gap between Average Cost of Supply (ACS) and Average Realizable Revenue (ARR).  The ACS-ARR Gap (on subsidy received basis, excluding Regulatory Income and UDAY Grant) has declined from Rs.0.69 per kwh in FY21 to Rs.0.22 per kwh in FY22.

 

It is well known that India has targeted to restrict its AT&C losses to below 15 per cent, and as such, the performance in FY22 augurs well towards this goal.

 

The Union power ministry has said that the decline of 5 percentage points in AT&C losses and Rs.0.47 in the ACS-ARR gap in one year is the result of a number of initiatives taken by the ministry that includes among other things revision in the prudential lending norms of the two leading financial institutions – PFC and REC. Discoms that need financing will need to commit to an action plan, endorsed by the respective state government, to reduce AT&C losses within a timeframe. Discoms that are seeking funding under the Rs.3-trillion RDSS will also need to adhere to a time-bound loss reduction trajectory.

 

All said, over the past two decades, the Central government (with different leaderships) is doing much to extricate state discoms from the financial mess that they are in. One must bear in mind that electricity is not a purely “Union” subject. It is more of a “State” subject with Central intervention merited only in deserving cases. However, it appears that most states tend to take Central support for granted. It is high time that state governments take full responsibility of their power value chain – most importantly the distribution part – and work towards resurrection.

 

Free electricity, or highly subsidized electricity, has traditionally been a popular political plank but there should be serious rethinking on this matter. Mobile telephony is a prospering business and has extremely deep penetration even in the lower socio-economic class. The idea of “free mobile telephony” would sound absurd even to the lower social rung that is happily paying for the service.

 

India’s per capita power consumption is way below the global average. There is huge demand for electricity – across all social strata – without any condition precedent of “free power”. Given this, power distribution can be an extremely profitable business but only if seen from a business perspective and not a political one.

 

(The author of this article, Venugopal Pillai, is Editor, T&D India. He may be reached on venugopal.pillai@tndindia.com.)

Intrastate transmission needs TBCB boost

Very recently, Power Grid Corporation of India Ltd (PGCIL) completed an intrastate scheme in Madhya Pradesh that it had won under the TBCB modality. In most likelihood, for Madhya Pradesh, this is the first or amongst the early transmission schemes developed using the TBCB philosophy.

 

PGCIL, the Central power transmission PSU, is already very active in the TBCB-based interregional/interstate power transmission landscape. That PGCIL is also taking keen interest in the intrastate network is a favourable augury to the state-level power grid, in general. PGCIL currently has three intrastate schemes — two in UP and one in MP. It plans to participate in more schemes in these and other states, as and when they come up for bidding.

 

The disconcerting point however is that not many states are coming forward in adopting the TBCB culture. Even progressive states – Maharashtra and Gujarat to name just two – have not featured the TBCB modality in their transmission network upgrade plans.

 

The TBCB intrastate transmission scheme that PGCIL recently completed in Madhya Pradesh (Bhind-Guna transmission project) had attracted big names. In fact, all the leading transmission developers showed interest. The e-reverse auction saw as many as 52 rounds, demonstrating the aggression that potential developers evinced. All this goes to prove that there is developer interest but there is a very limited project shelf currently available.

 

TBCB-based interregional transmission schemes are progressing quite well. PGCIL along with leading private developers like Sterlite Power and Adani Transmission are making useful contributions in enhancing this network, which ultimately adds to the National Grid capacity.

 

For electricity to reach the end-consumer, it is very important that intrastate grids are also developed concurrently. State power transmission utilities must appreciate that the TBCB route gives ample scope for induction of technology and managerial expertise, apart from project finance. These utilities can be assured of projects completed within the time and cost estimates. Uttar Pradesh, it may be recalled, had invoked the TBCB modality for developing an intrastate transmission scheme, involving 765kV lines, over a decade ago.

 

Meanwhile, under the Revamped Distribution Sector Scheme (RDSS), private entrepreneurs have a solid opportunity to contribute to upgrading the power distribution network, mainly through smart meter deployment. It is widely expected that the private sector will play a very important role in this Rs.3-trillion RDSS venture.

 

While power distribution is indeed the weakest link in the power value chain, power transmission is not much better off. The private sector can definitely play an important role if given the opportunity.

 

State transmission utilities will therefore stand to benefit if they open up a platform for seasoned transmission developers. And what platform could be better than TBCB?

 

(The author of this article, Venugopal Pillai, is Editor, T&D India. He may be reached on venugopal.pillai@tndindia.com.)

Fresh lease of life to privatization process

In a very significant recent development, Torrent Power moved closer to taking over power distribution in the Union Territory of Dadra & Nagar Haveli and Daman & Diu (DDN&DD). The Gujarat-based company, with a significant presence in the entire power value chain, has signed an agreement with the said UT administration to acquire controlling 51 per cent in the JV that will be responsible for power distribution activities in the UT of DNH&DD.

 

This is a major step forward for the government’s proposal, announced in May 2020, to privatize power distribution in all UTs.

 

The modality to be followed is the joint venture route where the private sector player will own 51 per cent equity stake (and management control) with the respective UT administration holding the remaining 49 per cent.

 

If matter progress well, power utility CESC will also take over power distribution in the UT of Chandigarh, on similar lines.

 

Privatization of power distribution of UTs is inherently different from the earlier attempts at privatization, which largely had to do with the asset-light distribution franchisee model. It must also be borne in mind that attempts at privatization were targeted in areas with high AT&C losses. However, in the case of UTs, the power distribution sector is not loss-making, if not highly profitable. This was precisely why several employee unions opposed the move, leading to some delay in finalizing the process.

 

The distribution franchisee model has not left a positive impression; there have been more failures and abortive attempts, than successes. What the government is now following is the distribution licensee model through the JV route where the private sector holds 51 per cent equity stake and management control, with the state government or UT administration holding the remaining 49 per cent.

 

This JV route has been phenomenally successful in Delhi, with Tata Power and Reliance ADAG Group being the private partners in two separate JVs. The recent attempt at similarly privatizing power distribution in Odisha, through four separate JVs with Tata Power, is also showing positive signs.

 

Power distribution is that area where the revenues for the entire power value chain are ultimately generated. It is also the only customer-facing link in the value chain. This being so, it is best that power distribution, in general, is handled by the private sector. Most state government discoms have a long legacy of commercial inefficiency. It is time that the private steps in.

 

While privatization needs to be pursued, it is also imperative that the much debated separation of “wire” and “supply” businesses of power distribution is implemented. This will bring more competition amongst private sector players in the “supply” side, which is in the ultimate interest of the end-consumer.

(Featured photograph, sourced from Torrent Power, shows replacement of electricity meters in Bhiwandi before and after Torrent Power took over as the distribution franchisee.)

(The author of this article, Venugopal Pillai, is Editor, T&D India. He may be reached on venugopal.pillai@tndindia.com.)